General regulations for the construction of Jzroof stone coated steel tile
1. The construction environment temperature should be 5℃~35℃. When the ambient temperature is lower than 5°C, take enhanced protective measures.
2. Construction personnel should wear rubber-soled soft shoes during construction, and try to avoid or reduce stepping on the laid tile surface. For parts that are easy to be stepped on, such as around the dormer window, soft materials should be used as temporary protection to avoid damage to the product .
3. Pipes, equipment or embedded parts passing through the roof waterproof layer must be installed before tile laying.
4. After the installation is completed, it is the final product. It is very important to ensure that the tile surface is not damaged during the whole installation process, so the following points should be noted:
4.1 Gloves must be worn when handling tile products on site, and they must be tied firmly when lifting and transported. They should be lifted gently and not dragged;
4.2 During the on-site cutting process, the bottom surface of the cutting machine should not be in direct contact with the tile surface, and a wooden board or rubber board is required;
4.3 When the construction personnel walk on the tiles, they must step on the joint part of the tile groove and the tile hanging strip, and it is strictly forbidden to jump, trample or randomly beat on the tiles;
4.4 The tools carried by the construction personnel should be placed in the tool bag, if they are placed on the roof, they should be placed on special cloth or other sheets;
4.5 Clean the iron filings and leftovers on the board surface. Iron filings will be generated during the cutting and drilling of the board surface. These iron filings and scraps must be removed in time and cannot be left overnight;
4.6 The used sealing rubber cartridges should be cleaned up in time.